Additional Texas wind farm groundbreaking timing
Company: Applied Digital
What the later record shows
Outcome not yet confirmed · happened April 1, 2024
The only 200 MW Texas wind-adjacent site in the evidence is the Garden City, TX campus, which the company sold to Marathon, closing April 1, 2024. No passage confirms the groundbreaking itself, and the link to this claim rests on matching location and scope.
“we expect our Texas facility will be largely supplied with power that is generated from wind, including power generated by the adjacent wind farm.”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗
“In March 2024, we announced that we entered into a definitive agreement to sell our 200 MW campus in Garden City, TX, to Marathon Digital Holdings (Nasdaq: MARA).”
2024-07-18 · Applied Digital 8-K filed 2024-07-19 View cached copy (2026-08-31)Live source ↗
“We completed the sale transaction on April 1, 2024.”
2024-07-18 · Applied Digital 8-K filed 2024-07-19 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
200MW targeted capacity Texas wind farm expected to break ground in late fiscal Q1 2023 or early fiscal Q2 2023
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “The Company is also progressing on several additional co-hosting facilities including an additional Texas wind farm with targeted capacity of 200MW, which is expected to break ground in late fiscal first quarter 2023 or early fiscal second quarter 2023.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release gives the additional Texas wind farm's 200MW target and its expected groundbreaking window.
Confirmed in the source:
- An additional Texas wind farm has a targeted capacity of 200MW
- It is expected to break ground in late fiscal Q1 2023 or early fiscal Q2 2023
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,855 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The Company is also progressing on several additional co-hosting facilities including an additional Texas wind farm with targeted capacity of 200MW, which is expected to break ground in late fiscal first quarter 2023 or early fiscal second quarter 2023.”