Marble campus substantial completion

Company: Core Scientific - Project: Marble

Subject kind
facility timeline
Statement date
2026-04-20
Promised by
2026-06-30
Current status
verified

What the later record shows

Delivered on time

The Q1 2026 earnings deck (May 6, 2026) lists Marble, NC (~65MW) as 'Fully handed over to customer', which is before the June 30, 2026 deadline. The Q2 deck shows Marble billing ~65 MW of ~65 MW leased. The exact handover date is not given, and the table layout makes the status-to-site mapping slightly uncertain.

“On track for midyear delivery Marble, NC Leased power: ~65MW Fully handed over to customer Austin, TX Leased power: ~20MW Fully handed over to customer”
2026-05-06 · First Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-26)Live source ↗Archive.org ↗
“Marble, NC ~65 MW Austin, TX ~20 MW Total ~590 MW Substantially complete Est. completion early 2027 ~260 ~30 ~70 ~65 ~20”
2026-07-28 · Second Quarter Fiscal Year 2026 Earnings Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Substantial completion of remaining Marble capacity expected in first half of 2026

Source (primary)

core-scientific 8-K exhibit (d149019dex992.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-09)Live source ↗

Quote: “substantial completion of the remaining MWs expected in the first half of 2026”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The document says about 37 MW at Marble are operational, with substantial completion of the remaining MWs expected in the first half of 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm) in full (44,283 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (d149019dex992.htm)

Quote: “substantial completion of the remaining MWs expected in the first half of 2026”

View cached copy (2026-09-09)Live source ↗

confirms Second Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Marble, NC ~65 MW Austin, TX ~20 MW Total ~590 MW Substantially complete Est. completion early 2027 ~260 ~30 ~70 ~65 ~20”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “On track for midyear delivery Marble, NC Leased power: ~65MW Fully handed over to customer Austin, TX Leased power: ~20MW Fully handed over to customer”

View cached copy (2026-09-26)Live source ↗Archive.org ↗

Record of changes

September 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.