Data Center Hosting Business bitcoin mining capacity
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Data Center Hosting Business operates 286 MW for bitcoin mining across North Dakota sites: 106 MW facility in Jamestown and 180 MW facility in Ellendale, operating at full capacity
Source (primary)
applied-digital 8-K exhibit (apldq426earningsreleaseasf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗
Quote: “As of May 31, 2026, the Company's 106 MW facility in Jamestown, ND, and 180 MW facility in Ellendale, ND, were operating at full capacity.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms applied-digital 8-K exhibit (apldq426earningsreleaseasf.htm)
Quote: “As of May 31, 2026, the Company's 106 MW facility in Jamestown, ND, and 180 MW facility in Ellendale, ND, were operating at full capacity.”