300 MW take-or-pay lease at Delta Forge 1

Company: Applied Digital - Project: Delta Forge 1

Subject kind
customer
Statement date
2026-07-26
Promised amount
7500.0 USD
Current status
stated

The claim, verbatim

Signed a 15-year take-or-pay lease with a high investment-grade hyperscaler for 300 MW at Delta Forge 1 in Boyce, Louisiana, providing approximately $7.5 billion in base-term contracted revenue with initial operations expected in calendar year 2027

Source (primary)

applied-digital 8-K exhibit (apldq426earningsreleaseasf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗

Quote: “Signed a 15-year take-or-pay lease with a new U.S. based, high investment-grade hyperscaler for 300 megawatts ("MW") of critical IT load at Delta Forge 1, a new AI Factory campus in Boyce, Louisiana. The lease provides for approximately $7.5 billion in base-term contracted revenue, with initial operations expected to commence calendar year 2027.”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The lease terms, location, revenue, and timing all appear verbatim.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487926000044/apldq426earningsreleaseasf.htm) in full (54,633 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apldq426earningsreleaseasf.htm)

Quote: “Signed a 15-year take-or-pay lease with a new U.S. based, high investment-grade hyperscaler for 300 megawatts ("MW") of critical IT load at Delta Forge 1, a new AI Factory campus in Boyce, Louisiana. The lease provides for approximately $7.5 billion in base-term contracted revenue, with initial operations expected to commence calendar year 2027.”

View cached copy (2026-09-02)Live source ↗