Corsicana Campus Development LOI
Company: Riot - Project: Corsicana
The claim, verbatim
Corsicana campus site under non-binding letter of intent with capacity potential of 1.3 GW or greater under advanced commercial and design discussions
Source (primary)
riot 8-K exhibit (riot-20260810xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-01)Live source ↗
Quote: “Advanced commercial and design discussions with full site under non-binding LOI to single tenant”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document states the full Corsicana site is under non-binding LOI with advanced commercial/design discussions and shows Corsicana LOI at 1.3 GW+.
Confirmed in the source:
- The Corsicana full site is under a non-binding LOI to a single tenant
- The site is under advanced commercial and design discussions
- The Corsicana campus has capacity potential of 1.3 GW or greater
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000110465926093406/riot-20260810xex99d2.htm) in full (26,006 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20260810xex99d2.htm)
Quote: “Advanced commercial and design discussions with full site under non-binding LOI to single tenant”