jain.com

Target of 100+ MW additional capacity online in 2027

Company: WhiteFiber

Subject kind
facility capacity
Statement date
2026-08-20
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

WhiteFiber targets bringing more than 100 MW of additional capacity online across its development pipeline in 2027.

Source (primary)

whitefiber 8-K exhibit (ea030292501ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-08-30)Live source ↗

Quote: “our target of bringing more than 100 MW of additional capacity online across our development pipeline in 2027”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states the target of bringing more than 100 MW of additional capacity online across the development pipeline in 2027.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026092599/ea030292501ex99-3.htm) in full (7,640 characters, retrieved August 30, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea030292501ex99-3.htm)

Quote: “our target of bringing more than 100 MW of additional capacity online across our development pipeline in 2027”

View cached copy (2026-08-30)Live source ↗