Sandersville facility expansion

Company: CleanSpark - Project: Sandersville

Subject kind
facility timeline
Statement date
2023-11-30
Promised by
2024-02-28
Promised amount
150.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

The 150 MW Sandersville development was reported as completed during 2024, but as of September 2024, 50 MW was still not energized and awaited a utility transformer. Energization in early 2024 was therefore only partial.

“During 2024, CleanSpark completed its development of an additional 150 MW at its data center in Sandersville, Georgia.”
2024-08-05 · CleanSpark S-4 filed 2024-08-06 View cached copy (2026-08-31)Live source ↗
“CleanSpark has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”
2024-09-22 · CleanSpark 424B3 filed 2024-09-23 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CleanSpark is developing a 150 MW expansion at its Sandersville, GA data center, expected to energize in early 2024, which will add over 6.0 EH/s to hashrate

Source (primary)

CleanSpark 10-K filed 2023-12-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are developing an additional 150 MW at our data center in Sandersville, GA, which is expected to energize in early 2024.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K states the 150 MW Sandersville development, its expected early-2024 energization, and that it will add over 6.0 EH/s.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017023067339/clsk-20230930.htm) in full (405,415 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2023-12-01

Quote: “We are developing an additional 150 MW at our data center in Sandersville, GA, which is expected to energize in early 2024.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.