Sandersville expansion timeline

Company: CleanSpark - Project: Sandersville

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2023-11-30
Promised by
2024-03-31
Promised amount
150.0 MW
Current status
delayed

What the later record shows

The date slipped

By May 2024 and again August 2024, after the March 31, 2024 target, filings said only 50 MW of the 150 MW Sandersville expansion was built and it was still not in service pending a utility transformer. No new date was given.

“The Company has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”
2024-05-08 · CleanSpark 10-Q filed 2024-05-09 View cached copy (2026-08-31)Live source ↗
“The Company has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”
2024-08-08 · CleanSpark 10-Q filed 2024-08-09 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

150 MW expansion at Sandersville data center expected to energize in early 2024, specifically early in the second fiscal quarter ending March 2024

Source (primary)

CleanSpark 10-K filed 2023-12-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are developing an additional 150 MW at our data center in Sandersville, GA, which is expected to energize in early 2024.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K's overview says the 150 MW Sandersville expansion is expected to energize in early 2024. Its facility description adds that completion is expected early in the second fiscal quarter ending March 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017023067339/clsk-20230930.htm) in full (405,415 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2023-12-01

Quote: “We are developing an additional 150 MW at our data center in Sandersville, GA, which is expected to energize in early 2024.”

View cached copy (2026-08-31)Live source ↗

delays CleanSpark 10-Q filed 2024-05-09

Quote: “The Company has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”

View cached copy (2026-08-31)Live source ↗

delays CleanSpark 10-Q filed 2024-08-09

Quote: “The Company has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.