Sandersville expansion hashrate addition

Company: CleanSpark - Project: Sandersville

Subject kind
facility capacity
Statement date
2023-11-30
Promised by
2024-02-28
Promised amount
6.0 EH/s
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

No passage gives the hashrate added by the Sandersville expansion. Later filings discuss only MW of infrastructure, with 50 MW still awaiting a transformer.

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Sandersville facility expansion will add over 6.0 exahashes per second to CleanSpark's hashrate capacity

Source (primary)

CleanSpark 10-K filed 2023-12-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Each building will house thousands of high-performance bitcoin mining machines and, once completed, will add over 6.0 EH/s to our hashrate.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K says the Sandersville buildings, once completed, will add over 6.0 EH/s to the company's hashrate.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017023067339/clsk-20230930.htm) in full (405,415 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2023-12-01

Quote: “Each building will house thousands of high-performance bitcoin mining machines and, once completed, will add over 6.0 EH/s to our hashrate.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.