Sandersville 150 MW expansion completion

Company: CleanSpark - Project: Sandersville

Subject kind
facility capacity
Statement date
2023-11-30
Promised by
2024-02-28
Promised amount
150.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

An August 2024 filing says the 150 MW development was completed during 2024. However, filings from March to September 2024 say 50 MW of that infrastructure was still waiting on a utility transformer before going into service, so the expansion was not fully done by the early-2024 target.

“We have completed an additional 50 MW of data center infrastructure in Sandersville, GA which is pending the commissioning of a utility transformer before it goes into service”
2024-03-27 · CleanSpark 424B5 filed 2024-03-28 View cached copy (2026-08-31)Live source ↗
“During 2024, CleanSpark completed its development of an additional 150 MW at its data center in Sandersville, Georgia.”
2024-08-05 · CleanSpark S-4 filed 2024-08-06 View cached copy (2026-08-31)Live source ↗
“CleanSpark has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”
2024-09-22 · CleanSpark 424B3 filed 2024-09-23 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

150 MW capacity expansion at Sandersville data center expected to be completed in early Q2 fiscal year 2024

Source (primary)

CleanSpark 10-K filed 2023-12-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The site is undergoing a 150 MW expansion with expected completion early in our second fiscal quarter ending March 2024.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K states the Sandersville site is undergoing a 150 MW expansion with expected completion early in the second fiscal quarter ending March 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017023067339/clsk-20230930.htm) in full (405,415 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-K filed 2023-12-01

Quote: “The site is undergoing a 150 MW expansion with expected completion early in our second fiscal quarter ending March 2024.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.