Total North Dakota hosting capacity 280MW

Company: Applied Digital

Subject kind
facility capacity
Statement date
2023-06-22
Promised amount
280.0 MW
Current status
stated

The claim, verbatim

The Ellendale facility brings Applied Digital to 280MW of total hosting power across its North Dakota facilities.

Source (primary)

applied-digital 8-K exhibit (applieddigital_ellendaleri.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-22)Live source ↗

Quote: “The addition of the latest facility will bring Applied to 280MW of total hosting power across its facilities in North Dakota.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms applied-digital 8-K exhibit (applieddigital_ellendaleri.htm)

Quote: “The addition of the latest facility will bring Applied to 280MW of total hosting power across its facilities in North Dakota.”

View cached copy (2026-11-22)Live source ↗