Building G replacement dry coolers arrival
Company: Riot
What the later record shows
Delivered; the record does not say when
The November 7, 2023 release says the replacement dry coolers had been received and over half installed. It does not say whether they arrived in August as promised.
“Replacement dry coolers for repairing Building G have been received and over half of the replacement dry coolers have been installed.”
2023-11-07 · riot 8-K exhibit (riot-20231107xex99d1.htm) View cached copy (2026-11-17)Live source ↗
Checked November 22, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Replacement dry coolers for repairing storm-damaged Building G have begun shipping and are due to arrive in August 2023.
Source (primary)
riot 8-K exhibit (riot-20230809xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-22)Live source ↗
Quote: “Replacement dry coolers for repairing Building G have begun shipping and are due to arrive in August.”
How we checked this
Checked on November 23, 2026. The cited source supports every part of this claim.
The August 9, 2023 release says Building G was damaged in the December 2022 winter storm and that replacement dry coolers have begun shipping and are due in August.
Confirmed in the source:
- Building G was damaged in a severe winter storm in Texas in December 2022
- Replacement dry coolers for repairing Building G have begun shipping
- The dry coolers are due to arrive in August 2023
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741923000021/riot-20230809xex99d1.htm) in full (21,912 characters, retrieved November 22, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20230809xex99d1.htm)
Quote: “Replacement dry coolers for repairing Building G have begun shipping and are due to arrive in August.”
confirms riot 8-K exhibit (riot-20231107xex99d1.htm)
Quote: “Replacement dry coolers for repairing Building G have been received and over half of the replacement dry coolers have been installed.”