Current data center hosting capacity
Company: Applied Digital
The claim, verbatim
Total hosting capacity of 286 MW across Jamestown (106 MW) and Ellendale (180 MW) for crypto data center hosting
Source (primary)
Applied Digital 10-K filed 2024-08-30 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW: • Jamestown, North Dakota: 106 MW facility. • Ellendale, North Dakota: 180 MW facility.”
How we checked this
Checked on September 18, 2026. The cited source supports every part of this claim.
The 10-K states the Data Center Hosting Business operates Jamestown (106 MW) and Ellendale (180 MW) sites, about 286 MW in total.
Confirmed in the source:
- Applied Digital's total crypto data center hosting capacity is approximately 286 MW
- The Jamestown, North Dakota facility is 106 MW
- The Ellendale, North Dakota facility is 180 MW
- These sites serve the crypto mining (Data Center Hosting) business
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000216/apld-20240531.htm) in full (481,620 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 10-K filed 2024-08-30
Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW: • Jamestown, North Dakota: 106 MW facility. • Ellendale, North Dakota: 180 MW facility.”