HPC Ellendale Facility operational timeline

Company: Applied Digital

Subject kind
guidance
Statement date
2024-09-10
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered on time

The Ellendale 100 MW HPC facility, the first Polaris Forge campus in Ellendale, achieved Ready-for-Service on schedule. Lease revenue began in the quarter ended November 30, 2025, which is within calendar 2025.

“Achieved Ready‑for‑Service at Polaris Forge 1, delivering 100 MW on schedule and fully energizing the first building (ELN-02)”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The Company began recognizing revenue associated with certain of its data center leases as accounted for under ASC 842 in the second quarter of the current fiscal year.”
2026-04-07 · Applied Digital 10-Q filed 2026-04-08 View cached copy (2026-08-30)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

HPC Ellendale Facility expected to become operational in calendar year 2025 with meaningful revenue generation anticipated

Source (primary)

Applied Digital S-1 filed 2024-09-11 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We anticipate that this business segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected in calendar year 2025.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The September 2024 S-1 states the company anticipates the HPC segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected in calendar year 2025. Both parts of the claim appear in the filing as company expectations, not as completed events.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000241/apld-cimresalesx1.htm) in full (112,203 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1 filed 2024-09-11

Quote: “We anticipate that this business segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected in calendar year 2025.”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-Q filed 2026-04-08

Quote: “The Company began recognizing revenue associated with certain of its data center leases as accounted for under ASC 842 in the second quarter of the current fiscal year.”

View cached copy (2026-08-30)Live source ↗

confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)

Quote: “Achieved Ready‑for‑Service at Polaris Forge 1, delivering 100 MW on schedule and fully energizing the first building (ELN-02)”

View cached copy (2026-09-22)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.