jain.com

Bitcoin mining capacity in Winfield, Oneida, and Tazewell, Tennessee

Company: CleanSpark - Project: Tazewell

Subject kind
facility capacity
Statement date
2024-09-10
Promised amount
40.0 MW
Current status
stated

The claim, verbatim

40 megawatts of bitcoin mining operating capacity in Winfield, TN; Oneida, TN; and Tazewell, TN

Source (primary)

CleanSpark 8-K filed 2024-09-11 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Winfield, TN; Oneida, TN; and Tazewell, TN: 40 megawatts”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 8-K filed 2024-09-11

Quote: “Winfield, TN; Oneida, TN; and Tazewell, TN: 40 megawatts”

View cached copy (2026-08-31)Live source ↗