Long Ridge plant 505 MW nameplate, 485 MW authorized
Company: Marathon Digital - Project: Long Ridge
The claim, verbatim
The Hannibal, Ohio combined-cycle gas plant has 505 MW nameplate capacity and is currently authorized to sell 485 MW.
Source (primary)
MARA Holdings Prices $185 Million 8.75% Senior Secured Notes to Fund $1.5 Billion Long Ridge Energy Acquisition - Crowdfund Insider (-, news_article)
View cached copy (2026-11-20)Live source ↗
Quote: “The plant has a nameplate capacity of 505 megawatts, although it is currently authorized to sell 485 megawatts”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The article describes the Hannibal, Ohio combined-cycle gas plant as having 505 MW of nameplate capacity and current authorization to sell 485 MW.
Confirmed in the source:
- The plant is a combined-cycle natural-gas power plant in Hannibal, Ohio
- The plant has a nameplate capacity of 505 MW
- The plant is currently authorized to sell 485 MW
What we did: Read our cached copy of the publisher (https://www.crowdfundinsider.com/2026/11/323799-mara-holdings-prices-185-million-8-75-senior-secured-notes-to-fund-1-5-billion-long-ridge-energy-acquisition/) in full (112,825 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms MARA Holdings Prices $185 Million 8.75% Senior Secured Notes to Fund $1.5 Billion Long Ridge Energy Acquisition - Crowdfund Insider
Quote: “The plant has a nameplate capacity of 505 megawatts, although it is currently authorized to sell 485 megawatts”