jain.com

CoreWeave hosting agreement total capacity

Company: CoreWeave

Subject kind
facility capacity
Statement date
2026-11-19
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

The Core Scientific hosting arrangement with CoreWeave covers 500 MW of capacity.

Source (primary)

Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal - Construction Review (-, news_article)
View cached copy (2026-11-20)Live source ↗Archive.org ↗

Quote: “The Muskogee facility forms part of a broader 500 MW hosting agreement between Core Scientific and CoreWeave.”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The article states the broader Core Scientific–CoreWeave hosting agreement is 500 MW.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://constructionreviewonline.com/core-scientifics-100-mw-muskogee-ai-data-center-advances-under-8-7b-coreweave-deal/) in full (14,910 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal - Construction Review

Quote: “The Muskogee facility forms part of a broader 500 MW hosting agreement between Core Scientific and CoreWeave.”

View cached copy (2026-11-20)Live source ↗Archive.org ↗