CoreWeave 500 MW hosting agreement with Core Scientific
Company: CoreWeave
The claim, verbatim
CoreWeave has a 500 MW HPC hosting agreement with Core Scientific with a potential value of about $8.7 billion over 12-year contract terms, each with two five-year extension options.
Source (primary)
Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal - Construction Review (-, news_article)
View cached copy (2026-11-20)Live source ↗Archive.org ↗
Quote: “The agreement carries a potential value of approximately $8.7 billion over 12-year contract terms, with each contract offering two five-year extension options.”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The article and its factsheet describe a 500 MW HPC hosting agreement with these value and term details.
Confirmed in the source:
- CoreWeave has a 500 MW HPC hosting agreement with Core Scientific
- The agreement has a potential value of approximately $8.7 billion
- The contract terms are 12 years
- Each contract has two five-year extension options
What we did: Read our cached copy of the publisher (https://constructionreviewonline.com/core-scientifics-100-mw-muskogee-ai-data-center-advances-under-8-7b-coreweave-deal/) in full (14,910 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal - Construction Review
Quote: “The agreement carries a potential value of approximately $8.7 billion over 12-year contract terms, with each contract offering two five-year extension options.”