Garden City, Texas facility energization
Company: Marathon Digital - Project: Garden City
What the later record shows
Delivered; the record does not say when
Marathon bought the Garden City, Texas site from Applied Digital on April 1, 2024, and it was described as operational with 132 MW running, so it was energized. No passage says when energization began, so whether it came online in October 2023 cannot be told.
“On April 1, 2024, the Company acquired an operational bitcoin mining site located in Garden City, Texas with 132 megawatts of operational capacity”
2024-07-31 · Marathon Digital 10-Q filed 2024-08-01 View cached copy (2026-08-31)Live source ↗
“Garden City, Texas Colocated generation + grid 126 74 200 8.2”
2025-03-02 · Marathon Digital 10-K filed 2025-03-03 View cached copy (2026-08-31)Live source ↗
Checked November 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Energization of the Garden City, Texas facility, hosted by Applied, is still pending. Marathon believes the facility will start to come online in October 2023. It has 4.1 EH/s installed but not yet energized.
Source (primary)
marathon-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-18)Live source ↗
Quote: “Energization of the facility in Garden City, Texas is still pending. However, based on the latest updates, we believe the facility will start to come online this month.”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
Marathon's October 4, 2023 update says Garden City energization was still pending and expected to begin that month. Its site table lists Applied as host, with 4.1 EH/s installed and none energized.
Confirmed in the source:
- Energization of Marathon's Garden City, Texas facility was still pending as of the October 4, 2023 update
- Marathon's site table lists Applied as the host of the Garden City, Texas facility
- Marathon said it believed the Garden City facility would start to come online 'this month', meaning October 2023 given the October 4, 2023 release date
- Garden City had 4.1 EH/s installed and 0.0 EH/s energized in September 2023, so its installed capacity was not yet energized
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1507605/000149315223035668/ex99-1.htm) in full (11,000 characters, retrieved November 18, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms marathon-digital 8-K exhibit (ex99-1.htm)
Quote: “Energization of the facility in Garden City, Texas is still pending. However, based on the latest updates, we believe the facility will start to come online this month.”
confirms Marathon Digital 10-Q filed 2024-08-01
Quote: “On April 1, 2024, the Company acquired an operational bitcoin mining site located in Garden City, Texas with 132 megawatts of operational capacity”
confirms Marathon Digital 10-K filed 2025-03-03
Quote: “Garden City, Texas Colocated generation + grid 126 74 200 8.2”