HPC build cost ~$6MM/MW; 70-80% construction debt

Company: Applied Digital

Subject kind
financing
Statement date
2023-10-11
Promised amount
6000000.0 USD
Current status
stated

The claim, verbatim

Anticipated HPC build cost of about $6MM per MW, targeting 70%-80% of construction cost financed by a traditional construction facility, with equity potentially funded by a partner.

Source (primary)

applied-digital 8-K exhibit (cfosummary10122023.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-18)Live source ↗

Quote: “Anticipated build cost of ~$6 MM per MW for our new design. Targeting 70% to 80% of construction cost financed by a traditional construction facility, with the equity portion potentially funded by a partner.”

How we checked this

Checked on November 20, 2026. The cited source supports every part of this claim.

The HPC slide states the build cost, construction financing target, and possible partner equity funding.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000216/cfosummary10122023.htm) in full (14,209 characters, retrieved November 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (cfosummary10122023.htm)

Quote: “Anticipated build cost of ~$6 MM per MW for our new design. Targeting 70% to 80% of construction cost financed by a traditional construction facility, with the equity portion potentially funded by a partner.”