Quinlan data center $1.3B build completion

Company: Core Scientific

Subject kind
facility timeline
Statement date
2026-11-13
Promised by
2028-09-04
Promised amount
1300000000.0 USD
Current status
stated

The claim, verbatim

The $1.3 billion Quinlan data center building and related work has an estimated completion date of Sept. 4, 2028.

Source (primary)

Core Scientific Plans $1.3B Data Center Build Outside Dallas - TheEnergyMag (-, news_article)
View cached copy (2026-11-18)Live source ↗

Quote: “Sept. 4, 2028, as the estimated completion date”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Core Scientific Plans $1.3B Data Center Build Outside Dallas - TheEnergyMag

Quote: “Sept. 4, 2028, as the estimated completion date”

View cached copy (2026-11-18)Live source ↗