AMD and neocloud leases ~530 MW
Company: Core Scientific
The claim, verbatim
In July, Core Scientific signed leases with AMD and an unnamed neocloud for about 530 MW of critical IT capacity across five sites, each for 15 years with three five-year options.
Source (primary)
Core Scientific files for a $1.3 billion data center building near Dallas at the campus where AMD plans to lease 110 megawatts - MLQ.ai (-, news_article)
View cached copy (2026-11-18)Live source ↗
Quote: “Core Scientific signed leases with AMD and an unnamed neocloud for about 530 MW of critical IT capacity across five of its sites, each for 15 years with three five-year options”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Core Scientific files for a $1.3 billion data center building near Dallas at the campus where AMD plans to lease 110 megawatts - MLQ.ai
Quote: “Core Scientific signed leases with AMD and an unnamed neocloud for about 530 MW of critical IT capacity across five of its sites, each for 15 years with three five-year options”