Corsicana first batch of miners online
Company: Riot
What the later record shows
Delivered late · happened April 30, 2024
The 10-Q states Corsicana operations began in April 2024, after the promised Q1 2024 timing.
“Operations of this initial phase of the development commenced in April 2024, following energization of the substation.”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot plans to bring the first batch of miners online at the Corsicana Facility in Q1 2024.
Source (primary)
riot 8-K exhibit (riot-20231107xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “Q1 2024 First Batch of Miners Online”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20231107xex99d2.htm)
Quote: “Q1 2024 First Batch of Miners Online”
confirms Riot 10-Q filed 2024-07-31
Quote: “Operations of this initial phase of the development commenced in April 2024, following energization of the substation.”