Corsicana Building A1 erection
Company: Riot
What the later record shows
Delivered; the record does not say when
Building A1 had been erected and fully completed as of June 30, 2024. No passage says when the erection itself happened, so whether it met Q4 2023 cannot be told.
“16.7 EH/s once fully deployed in 4Q24 ▪ Building A1 fully developed ▪ Deployment in A2 and B1 ongoing”
2024-06-12 · riot 8-K exhibit (riot-20240613xex99d1.htm) View cached copy (2026-11-03)Live source ↗
“As of June 30, 2024, the first 100 MW building, Building A1, was completed and the second 100 MW building”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The planned Corsicana Phase 1 timeline calls for Building A1 erection in Q4 2023.
Source (primary)
riot 8-K exhibit (riot-20231107xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “Q4 2023 Building A1 Erection”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20231107xex99d2.htm)
Quote: “Q4 2023 Building A1 Erection”
confirms Riot 10-Q filed 2024-07-31
Quote: “As of June 30, 2024, the first 100 MW building, Building A1, was completed and the second 100 MW building”
confirms riot 8-K exhibit (riot-20240613xex99d1.htm)
Quote: “16.7 EH/s once fully deployed in 4Q24 ▪ Building A1 fully developed ▪ Deployment in A2 and B1 ongoing”