Corsicana tanks commissioning

Company: Riot

Subject kind
facility timeline
Statement date
2023-11-07
Promised by
2023-12-31
Current status
verified

What the later record shows

Delivered; the record does not say when

Corsicana operations, including operational immersion tanks, began in April 2024 after the substation was energized. No passage states when the tanks were commissioned relative to Q4 2023.

“Operations of this initial phase of the development commenced in April 2024, following energization of the substation.”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗

Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The planned Corsicana Phase 1 timeline calls for tanks commissioning in Q4 2023.

Source (primary)

riot 8-K exhibit (riot-20231107xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗

Quote: “Q4 2023 Tanks Commissioning”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20231107xex99d2.htm)

Quote: “Q4 2023 Tanks Commissioning”

View cached copy (2026-11-17)Live source ↗

confirms Riot 10-Q filed 2024-07-31

Quote: “Operations of this initial phase of the development commenced in April 2024, following energization of the substation.”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.