jain.com

Corsicana Facility Phase 1 400 MW build-out

Company: Riot

Subject kind
facility capacity
Statement date
2023-11-07
Promised amount
400.0 MW
Current status
stated

The claim, verbatim

Phase 1 of the Corsicana Facility, Riot's second large-scale facility (1 GW), comprises the buildout of an initial 400 MW of immersion-cooled data center infrastructure.

Source (primary)

riot 8-K exhibit (riot-20231107xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗

Quote: “Phase 1 of the Corsicana Facility development is comprised of the buildout of an initial 400 MW of immersion-cooled data center infrastructure.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20231107xex99d2.htm)

Quote: “Phase 1 of the Corsicana Facility development is comprised of the buildout of an initial 400 MW of immersion-cooled data center infrastructure.”

View cached copy (2026-11-17)Live source ↗