Corsicana Facility Phase 1 400 MW build-out
Company: Riot
The claim, verbatim
Phase 1 of the Corsicana Facility, Riot's second large-scale facility (1 GW), comprises the buildout of an initial 400 MW of immersion-cooled data center infrastructure.
Source (primary)
riot 8-K exhibit (riot-20231107xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “Phase 1 of the Corsicana Facility development is comprised of the buildout of an initial 400 MW of immersion-cooled data center infrastructure.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20231107xex99d2.htm)
Quote: “Phase 1 of the Corsicana Facility development is comprised of the buildout of an initial 400 MW of immersion-cooled data center infrastructure.”