Full deployment of 33,280-miner MicroBT order at Corsicana by mid-2024
Company: Riot
What the later record shows
The date slipped · new target December 31, 2024
In June 2024, deployment in A2 and B1 was still ongoing, and full Phase I deployment was guided to 4Q24 rather than mid-2024. No passage confirms when the specific 33,280-miner order was fully deployed.
“16.7 EH/s once fully deployed in 4Q24 ▪ Building A1 fully developed ▪ Deployment in A2 and B1 ongoing”
2024-06-12 · riot 8-K exhibit (riot-20240613xex99d1.htm) View cached copy (2026-11-03)Live source ↗
“As of June 30, 2024, the first 100 MW building, Building A1, was completed and the second 100 MW building”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot expects full deployment of the initial MicroBT order of 33,280 miners for its Corsicana Facility by mid-2024.
Source (primary)
riot 8-K exhibit (riot-20231107xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “an initial order of 33,280 Bitcoin miners for its Corsicana Facility... Upon full deployment of this initial order by mid-2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20231107xex99d1.htm)
Quote: “an initial order of 33,280 Bitcoin miners for its Corsicana Facility... Upon full deployment of this initial order by mid-2024”
delays Riot 10-Q filed 2024-07-31
Quote: “As of June 30, 2024, the first 100 MW building, Building A1, was completed and the second 100 MW building”
delays riot 8-K exhibit (riot-20240613xex99d1.htm)
Quote: “16.7 EH/s once fully deployed in 4Q24 ▪ Building A1 fully developed ▪ Deployment in A2 and B1 ongoing”