jain.com

Corsicana 910 MW data center lease

Company: Riot

Subject kind
customer
Statement date
2026-11-14
Promised amount
28000000000.0 USD
Current status
stated

The claim, verbatim

Riot disclosed a 15-year data center lease worth approximately $28 billion covering 910 MW of critical IT capacity at its Corsicana, Texas campus. CEO Jason Les called it the largest lease in Riot's history.

Source (primary)

Is KBW Wrong to Back Off Riot Platforms? Wall Street Still Sees $32 - TIKR.com (-, news_article)
View cached copy (2026-11-16)Live source ↗Archive.org ↗

Quote: “disclosed a 15-year, approximately $28 billion data center lease covering 910 megawatts of critical IT capacity at its Corsicana campus in Texas. Riot CEO Jason Les described the agreement as “the largest lease in Riot’s history,””

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/is-kbw-wrong-to-back-off-riot-platforms-wall-street-still-sees-32) in full (8,595 characters, retrieved November 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Is KBW Wrong to Back Off Riot Platforms? Wall Street Still Sees $32 - TIKR.com

Quote: “disclosed a 15-year, approximately $28 billion data center lease covering 910 megawatts of critical IT capacity at its Corsicana campus in Texas. Riot CEO Jason Les described the agreement as “the largest lease in Riot’s history,””