Hunt County campus leasable capacity at full power
Company: Core Scientific
The claim, verbatim
The Hunt County campus could support up to 285MW of leasable capacity (430MW gross) across multiple buildings, reaching full power by 2029.
Source (primary)
Core Scientific files for 285MW data center outside Dallas, Texas (-, news_article)
View cached copy (2026-11-16)Live source ↗Archive.org ↗
Quote: “the campus could support up to 285MW of leasable capacity (430MW gross capacity) across multiple buildings, with the site could begin energizing in 2027, and reaching full power by 2029”
How we checked this
Additional evidence
confirms Core Scientific files for 285MW data center outside Dallas, Texas
Quote: “the campus could support up to 285MW of leasable capacity (430MW gross capacity) across multiple buildings, with the site could begin energizing in 2027, and reaching full power by 2029”