Delivery and deployment of 66,560 new miners begins H2 2024
Company: Riot
What the later record shows
Delivered on time
By October 2024, 89,438 miners had been received and all were energized. That exceeds the first order (33,280) plus the Rockdale order (31,500), so deliveries and deployment of the second order had begun before the end of 2024.
“Riot has received a total of 89,438 miners from this order to date”
2024-10-29 · riot 8-K exhibit (riot-20241030xex99d2.htm) View cached copy (2026-10-25)Live source ↗
“All of these miners are currently energized with the remaining balance of 41,902 miners to be received and deployed through the end of 2024”
2024-10-29 · riot 8-K exhibit (riot-20241030xex99d2.htm) View cached copy (2026-10-25)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Delivery and deployment of the new order of 66,560 MicroBT miners is expected to begin in the second half of 2024.
Source (primary)
riot 8-K exhibit (riot-20231204xex99d3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “H2 2024: Delivery and deployment begins for the new purchase order of 66,560 additional MicroBT miners”
How we checked this
Additional evidence
confirms riot 8-K exhibit (riot-20231204xex99d3.htm)
Quote: “H2 2024: Delivery and deployment begins for the new purchase order of 66,560 additional MicroBT miners”
confirms riot 8-K exhibit (riot-20241030xex99d2.htm)
Quote: “Riot has received a total of 89,438 miners from this order to date”