Additional 200 MW immersion-cooled miners by Q2 2024
Company: Riot
What the later record shows
Outcome not yet confirmed
Corsicana began operating in April 2024, and 64,488 MicroBT miners were energized by late July 2024. No passage states that 200 MW of immersion-cooled miners was online by Q2 2024.
“64,488 of those miners are currently energized with the remaining balance to be installed and energized during the third quarter”
2024-07-30 · riot 8-K exhibit (riot-20240731xex99d2.htm) View cached copy (2026-11-01)Live source ↗
“These miners are primarily for use at the Corsicana Facility, which commenced operations in April 2024.”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot has a pathway to deploy an additional 200 MW of immersion-cooled miners by Q2 2024.
Source (primary)
riot 8-K exhibit (riot-20231204xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “Provides clear pathway to deploying an additional 200 MW of immersion-cooled miners by Q2 2024”
How we checked this
Additional evidence
confirms riot 8-K exhibit (riot-20231204xex99d2.htm)
Quote: “Provides clear pathway to deploying an additional 200 MW of immersion-cooled miners by Q2 2024”
Record of changes
November 16, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.