Sandersville 150 MW expansion completion

Company: CleanSpark - Project: Sandersville

Subject kind
facility timeline
Statement date
2023-12-07
Promised by
2023-12-31
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late

CleanSpark's S-4 (filed August 2024) says the 150 MW Sandersville expansion was completed during 2024, after the promised end-2023 date. No exact completion date is given, only that it happened in 2024 before the August 2024 filing.

“During 2024, CleanSpark completed its development of an additional 150 MW at its data center in Sandersville, Georgia.”
2024-08-05 · CleanSpark S-4 filed 2024-08-06 View cached copy (2026-08-31)Live source ↗

Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Sandersville, Georgia site is undergoing a 150 MW expansion that CleanSpark expects to complete later in 2023.

Source (primary)

cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/827876/000095017023069052/clsk-ex99_1.htm) in full (34,954 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)

Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”

View cached copy (2026-11-15)Live source ↗

confirms CleanSpark S-4 filed 2024-08-06

Quote: “During 2024, CleanSpark completed its development of an additional 150 MW at its data center in Sandersville, Georgia.”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 16, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 16, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.