Sandersville 150 MW expansion completion
Company: CleanSpark - Project: Sandersville
What the later record shows
Delivered late
CleanSpark's S-4 (filed August 2024) says the 150 MW Sandersville expansion was completed during 2024, after the promised end-2023 date. No exact completion date is given, only that it happened in 2024 before the August 2024 filing.
“During 2024, CleanSpark completed its development of an additional 150 MW at its data center in Sandersville, Georgia.”
2024-08-05 · CleanSpark S-4 filed 2024-08-06 View cached copy (2026-08-31)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Sandersville, Georgia site is undergoing a 150 MW expansion that CleanSpark expects to complete later in 2023.
Source (primary)
cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”
How we checked this
Additional evidence
confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)
Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”
confirms CleanSpark S-4 filed 2024-08-06
Quote: “During 2024, CleanSpark completed its development of an additional 150 MW at its data center in Sandersville, Georgia.”