NC-1 development cost per MW
Company: WhiteFiber
The claim, verbatim
NC-1 development costs are expected to finish just below $9 million per gross megawatt, within the original $7-9 million range.
Source (primary)
WhiteFiber Q3 Earnings Call Highlights - MarketBeat (-, news_article)
View cached copy (2026-11-15)Live source ↗Archive.org ↗
Quote: “Development costs are expected to finish just below $9 million per gross megawatt”
How we checked this
Checked on November 16, 2026. The cited source supports every part of this claim.
The article states both the just-below-$9 million per gross megawatt estimate and that it falls within the original $7–9 million range.
Confirmed in the source:
- NC-1 development costs are expected to finish just below $9 million per gross megawatt
- This is within the company's original $7 million to $9 million range
What we did: Read our cached copy of the publisher (https://www.marketbeat.com/instant-alerts/transcript-whitefiber-q3-earnings-call-highlights-2026-11-10/) in full (18,409 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber Q3 Earnings Call Highlights - MarketBeat
Quote: “Development costs are expected to finish just below $9 million per gross megawatt”