245 MW Louisiana data center with Fluidstack

Company: Hut 8 - Project: River Bend

Subject kind
facility timeline
Statement date
2026-08-31
Promised by
2027-06-30
Promised amount
7000000000.0 USD
Current status
stated

The claim, verbatim

Hut 8 signed a 15-year, $7 billion lease with Fluidstack to develop 245 MW of AI data-center capacity at its River Bend campus in Louisiana, with first data halls expected online in Q2 2027.

Source (primary)

Why Is HUT Stock Rising Nearly 5% In Overnight Trading? - stocktwits.com (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “In Dec. 2025, Hut 8 signed a 15-year, $7 billion lease with Fluidstack to develop 245 MW of AI data-center capacity at its River Bend campus in Louisiana... with the first data halls expected to come online in Q2 2027.”

How we checked this

Checked on September 17, 2026. The cited source supports every part of this claim.

The article states that in December 2025 Hut 8 signed a 15-year, $7 billion lease with Fluidstack for 245 MW at River Bend, Louisiana. It gives Q2 2027 as the expected date for the first data halls.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://stocktwits.com/news-articles/markets/equity/why-is-hut-stock-rising-nearly-5-in-overnight-trading/cZsocQzRJt5) in full (5,828 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Why Is HUT Stock Rising Nearly 5% In Overnight Trading? - stocktwits.com

Quote: “In Dec. 2025, Hut 8 signed a 15-year, $7 billion lease with Fluidstack to develop 245 MW of AI data-center capacity at its River Bend campus in Louisiana... with the first data halls expected to come online in Q2 2027.”

View cached copy (2026-09-01)Live source ↗