River Bend construction progress

Company: Hut 8 - Project: River Bend

Subject kind
facility timeline
Statement date
2026-11-09
Current status
stated

The claim, verbatim

At River Bend, structural steel and foundations are complete across all four computing halls and the campus substation has been initially energized.

Source (primary)

Hut 8 (TSX:HUT): Is It Becoming an AI Infrastructure Powerhouse? - Kalkine Media (-, news_article)
View cached copy (2026-11-13)Live source ↗Archive.org ↗

Quote: “Structural steel and foundations are complete across all four computing halls, and the campus substation has been initially energized.”

How we checked this

Checked on November 16, 2026. The cited source supports every part of this claim.

The article states that structural steel and foundations are complete across all four River Bend computing halls and that the campus substation has been initially energized.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://kalkinemedia.com/ca/stocks/financial/hut-8-tsxhut-is-it-becoming-an-ai-infrastructure-powerhouse) in full (18,920 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Hut 8 (TSX:HUT): Is It Becoming an AI Infrastructure Powerhouse? - Kalkine Media

Quote: “Structural steel and foundations are complete across all four computing halls, and the campus substation has been initially energized.”