Road repairs within 180 days after construction
Company: Applied Digital
The claim, verbatim
Section 7.07 requires Applied Digital to complete local road repairs within 180 days after construction finishes.
Source (primary)
England Authority sets stage for final vote on Applied Digital data center PILOT agreement - KALB | News Channel 5 (-, news_article)
View cached copy (2026-11-13)Live source ↗Archive.org ↗
Quote: “Section 7.07 of the document establishes that repairs must be completed within 180 days after construction finishes.”
How we checked this
Checked on November 14, 2026. The cited source supports every part of this claim.
The article states that the PILOT compels Applied Digital to take care of local roads, and that under Section 7.07 repairs must be completed within 180 days after construction.
Confirmed in the source:
- Section 7.07 of the PILOT addresses local road repairs by Applied Digital
- Repairs must be completed within 180 days after construction finishes
What we did: Read our cached copy of the publisher (https://www.kalb.com/2026/11/12/england-authority-sets-stage-final-vote-applied-digital-data-center-pilot-agreement/) in full (10,841 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms England Authority sets stage for final vote on Applied Digital data center PILOT agreement - KALB | News Channel 5
Quote: “Section 7.07 of the document establishes that repairs must be completed within 180 days after construction finishes.”