The claim, verbatim
The PILOT sets a payment schedule for a $4M community benefit deal for Boyce, paid over tax years 2028-2030.
Source (primary)
England Authority sets stage for final vote on Applied Digital data center PILOT agreement - KALB | News Channel 5 (-, news_article)
View cached copy (2026-11-13)Live source ↗Archive.org ↗
Quote: “The PILOT also outlines the payment schedule for a $4 million community benefit deal for Boyce.”
How we checked this
Checked on November 14, 2026. The cited source supports every part of this claim.
The article describes the $4 million Boyce community benefit deal and shows a payment table covering 2028, 2029 and 2030.
Confirmed in the source:
- The PILOT sets a payment schedule for a community benefit deal for Boyce
- The Boyce deal totals $4M
- The Boyce payments are made over tax years 2028-2030
What we did: Read our cached copy of the publisher (https://www.kalb.com/2026/11/12/england-authority-sets-stage-final-vote-applied-digital-data-center-pilot-agreement/) in full (10,841 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms England Authority sets stage for final vote on Applied Digital data center PILOT agreement - KALB | News Channel 5