Deploy ~12,000 Bitmain S21 miners by mid-2024
Company: Core Scientific
What the later record shows
The date slipped · new target July 31, 2024
In February 2024 the company moved the target to the end of July 2024, for 12,600 S21 miners. A later filing says all of the roughly 12,900 S21 miners had been received by December 31, 2024, but no passage says when they were deployed.
“Core Scientific expects to deploy an additional 12,600 Bitmain S21 miners by the end of July 2024, representing 2.5 EH/s in energized hash rate”
2024-02-04 · core-scientific 8-K exhibit (januarypressrelease.htm) View cached copy (2026-11-12)Live source ↗
“The second agreement was for the acquisition of Antminer S21 miners with a combined exahash of 2.5 or approximately 12,900 miners.”
2026-03-01 · Core Scientific 10-K/A filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
“As of December 31, 2024, the Company had received all of the miners and completed all 2024 payments due on miners ordered for deployment this year.”
2026-03-01 · Core Scientific 10-K/A filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
Checked November 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company expects to deploy about 12,000 Bitmain S21 miners before mid-year 2024.
Source (primary)
core-scientific 8-K exhibit (d661343dex993.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-13)Live source ↗
Quote: “expects to deploy approximately 12,000 Bitmain S21 bitcoin miners before mid-year 2024”
How we checked this
Checked on November 14, 2026. The cited source supports every part of this claim.
The release states the company expects to deploy about 12,000 Bitmain S21 miners before mid-2024.
Confirmed in the source:
- Core Scientific expected to deploy approximately 12,000 Bitmain S21 miners before mid-year 2024
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000119312524013078/d661343dex993.htm) in full (10,311 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms core-scientific 8-K exhibit (d661343dex993.htm)
Quote: “expects to deploy approximately 12,000 Bitmain S21 bitcoin miners before mid-year 2024”
delays Core Scientific 10-K/A filed 2026-03-02
Quote: “The second agreement was for the acquisition of Antminer S21 miners with a combined exahash of 2.5 or approximately 12,900 miners.”
delays core-scientific 8-K exhibit (januarypressrelease.htm)
Quote: “Core Scientific expects to deploy an additional 12,600 Bitmain S21 miners by the end of July 2024, representing 2.5 EH/s in energized hash rate”