Corsicana total capital cost estimate

Company: Riot

Subject kind
guidance
Statement date
2026-11-10
Promised amount
5500000000.0 USD
Current status
stated

The claim, verbatim

Riot estimates total capital costs for the Corsicana project at $5.5 billion, or approximately $6 million per IT MW.

Source (primary)

Riot Platforms leases 910 MW Texas data center for US$28 billion - ET Datacenters (-, news_article)
View cached copy (2026-11-10)Live source ↗Archive.org ↗

Quote: “Riot estimates total capital costs for the project at US$5.5 billion.”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The article gives both the total capital cost estimate and the per-megawatt equivalent.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://datacenters.economictimes.indiatimes.com/news/investments-deals/riot-platforms-leases-910-mw-texas-data-center-for-us28-billion/135674691) in full (3,563 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms leases 910 MW Texas data center for US$28 billion - ET Datacenters

Quote: “Riot estimates total capital costs for the project at US$5.5 billion.”

View cached copy (2026-11-10)Live source ↗Archive.org ↗