jain.com

Corsicana total capital cost estimate

Company: Riot

Subject kind
guidance
Statement date
2026-11-09
Promised amount
5500000000.0 USD
Current status
stated

The claim, verbatim

Riot estimates total capital costs for the project at $5.5 billion, approximately $6 million per IT MW.

Source (primary)

Riot Platforms leases 910 MW Texas data center for US$28 billion - ET Datacenters (-, news_article)
View cached copy (2026-11-10)Live source ↗Archive.org ↗

Quote: “Riot estimates total capital costs for the project at US$5.5 billion. This equates to approximately US$6 million per IT MW.”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The article reports both the total capital cost estimate and the per-MW figure.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://datacenters.economictimes.indiatimes.com/news/investments-deals/riot-platforms-leases-910-mw-texas-data-center-for-us28-billion/135674691) in full (3,563 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms leases 910 MW Texas data center for US$28 billion - ET Datacenters

Quote: “Riot estimates total capital costs for the project at US$5.5 billion. This equates to approximately US$6 million per IT MW.”

View cached copy (2026-11-10)Live source ↗Archive.org ↗