MicroBT second miner order delivery
Company: Riot
What the later record shows
Outcome not yet confirmed
The passages only restate the expected delivery and payment schedule through about April 2025 or mid-2025. None states that the 66,560 miners in the second order were fully delivered.
“The remaining commitment of approximately $252.8 million is due in installments through approximately April 2025 based on the estimated miner delivery schedule.”
2024-08-08 · riot 8-K exhibit (riot-20231231xex99d2.htm) View cached copy (2026-10-31)Live source ↗
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Second MicroBT order of 66,560 miners for the next four Corsicana buildings at $16/TH, with remaining $223 million due, is scheduled to be delivered through April 2025.
Source (primary)
riot 8-K exhibit (riot-20240222xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗
Quote: “Includes remaining $223 million on second order of 66,560 additional miners scheduled to be delivered through April 2025.”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The presentation states the order's size, intended buildings, price, remaining $223 million and delivery schedule through April 2025.
Confirmed in the source:
- Riot's second MicroBT order covers 66,560 miners
- The second order is for the next four buildings at the Corsicana facility
- The second order is priced at $16/TH
- $223 million remains on the second order
- The second-order miners are scheduled to be delivered through April 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d2.htm) in full (20,192 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240222xex99d2.htm)
Quote: “Includes remaining $223 million on second order of 66,560 additional miners scheduled to be delivered through April 2025.”