The claim, verbatim
Up to 600 gross MW of Critical IT load / AI at the Hannibal campus through 2030.
Source (primary)
MARA to Accelerate its Digital Infrastructure Strategy with Acquisition of Long Ridge Energy & Power (“Long Ridge”) Presentation (IR page (ir.mara.com), ir_presentation)
View cached copy (2026-11-10)Live source ↗Archive.org ↗
Quote: “600 Gross MW of Critical IT Load / AI Through 2030”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The deck states up to 600 gross MW of Critical IT load / AI for the campus and ties the 600 MW figure to the period through 2030.
Confirmed in the source:
- The Hannibal campus is presented as having up to 600 gross MW of Critical IT load / AI
- The 600 gross MW figure is presented through 2030
What we did: Read our cached copy of IR page (ir.mara.com) (https://d1io3yog0oux5.cloudfront.net/_8c69f4357a699e228a85d68890478b48/marathondh/db/417/7572/pdf/Project+Leopard+Deck+V2.pdf) in full (19,483 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms MARA to Accelerate its Digital Infrastructure Strategy with Acquisition of Long Ridge Energy & Power (“Long Ridge”) Presentation
Quote: “600 Gross MW of Critical IT Load / AI Through 2030”