No reduction of PJM grid supply
Company: Marathon Digital - Project: Long Ridge
The claim, verbatim
MARA does not expect to reduce Long Ridge's current capacity supply to the PJM grid; future compute demand at the site is expected to be supported by incremental generation developed over time.
Source (primary)
MARA Holdings, Inc. Receives FERC Approval For Acquisition Of Long Ridge Energy & Power LLC - www.marketscreener.com (-, news_article)
View cached copy (2026-11-08)Live source ↗
Quote: “MARA does not expect to reduce Long Ridge Energy?s current supply of capacity to the PJM grid or adversely impact consumers.”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The article says MARA does not expect to reduce Long Ridge's current capacity supply to PJM, and that future compute demand at the site is expected to be met by incremental generation developed over time.
Confirmed in the source:
- MARA does not expect to reduce Long Ridge Energy's current supply of capacity to the PJM grid
- Future compute demand created at the Long Ridge site is expected to be supported by incremental generation developed over time
What we did: Read our cached copy of the publisher (https://www.marketscreener.com/news/mara-holdings-inc-receives-ferc-approval-for-acquisition-of-long-ridge-energy-power-llc-ce785fd2d98ef62d) in full (15,407 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms MARA Holdings, Inc. Receives FERC Approval For Acquisition Of Long Ridge Energy & Power LLC - www.marketscreener.com
Quote: “MARA does not expect to reduce Long Ridge Energy?s current supply of capacity to the PJM grid or adversely impact consumers.”