Additional 100 MW expansion capacity at Garden City site, expansion expected later in 2024
Company: Marathon Digital - Project: Garden City
What the later record shows
The date slipped
In November 2024 Garden City was still 100 MW powered with only 'potential' to reach 200 MW. The 10-K table after year-end 2024 shows 126 MW operational and 74 MW still listed as growth capacity, so the 100 MW expansion was not done in 2024. No revised date was given.
“MARA’s Garden City, TX facility: 100 MW powered, 5.4 EH/s from 40,800 miners, adjacent to a wind farm, with potential to expand to 200 MW”
2024-11-11 · marathon-digital 8-K exhibit (ex99-1.htm) View cached copy (2026-10-25)Live source ↗
“Garden City, Texas Colocated generation + grid 126 74 200 8.2”
2025-03-02 · Marathon Digital 10-K filed 2025-03-03 View cached copy (2026-08-31)Live source ↗
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The acquisition gives Marathon an additional 100 megawatts of capacity in which to expand at the Garden City site, with the expansion anticipated later in 2024.
Source (primary)
marathon-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗
Quote: “an additional 100 megawatts of capacity in which to expand ... Following the anticipated expansion of this site later in the year”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
In the April 2, 2024 release, Marathon's CEO says the closing provides 'an additional 100 megawatts of capacity in which to expand' and refers to 'the anticipated expansion of this site later in the year,' meaning the Garden City site in 2024.
Confirmed in the source:
- Marathon's acquisition of the Garden City, Texas data center gave it an additional 100 megawatts of capacity in which to expand
- An expansion of the Garden City site was anticipated later in the year, which is 2024 given the April 2, 2024 release date
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1507605/000149315224013186/ex99-1.htm) in full (4,699 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms marathon-digital 8-K exhibit (ex99-1.htm)
Quote: “an additional 100 megawatts of capacity in which to expand ... Following the anticipated expansion of this site later in the year”
delays Marathon Digital 10-K filed 2025-03-03
Quote: “Garden City, Texas Colocated generation + grid 126 74 200 8.2”
delays marathon-digital 8-K exhibit (ex99-1.htm)
Quote: “MARA’s Garden City, TX facility: 100 MW powered, 5.4 EH/s from 40,800 miners, adjacent to a wind farm, with potential to expand to 200 MW”