Promised amount
280.0 MW
Current status
stated

The claim, verbatim

Applied Digital has approximately 280MW of data center capacity operating.

Source (primary)

applied-digital 8-K exhibit (apldraisesummit040324fin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “~280MW Operating”

How we checked this

Checked on November 9, 2026. The cited source supports every part of this claim.

The presentation's key segment stats include '~280MW Operating'.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000066/apldraisesummit040324fin.htm) in full (11,985 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apldraisesummit040324fin.htm)

Quote: “~280MW Operating”

View cached copy (2026-11-08)Live source ↗