Total contracted data-center capacity
Company: Riot
The claim, verbatim
With the Corsicana lease, the AMD contract and the Rockdale lease, Riot's contracted data-center capacity reached 1,151 MW and its long-term contracted revenue reached about $38 billion.
Source (primary)
Riot Platforms Reports Third-Quarter Results and Data Center Expansion - The Globe and Mail (-, news_article)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “the agreement brought Riot's contracted data-center capacity to 1,151 megawatts and long-term contracted revenue to approximately $38 billion”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot Platforms Reports Third-Quarter Results and Data Center Expansion - The Globe and Mail
Quote: “the agreement brought Riot's contracted data-center capacity to 1,151 megawatts and long-term contracted revenue to approximately $38 billion”