Initial HPC energization
Company: Core Scientific
What the later record shows
Delivered; the record does not say when
An October 2025 presentation says more than about 120 MW was energized at Denton and Marble, so HPC capacity under the CoreWeave contracts did come online. No passage says whether energization began in the first half of 2025.
“~120+ MW Energized Across Denton & Marble Sites”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core Scientific's illustrative CoreWeave contract timeline shows HPC MW energized in the first half of 2025.
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “HPC MW energized in 1H of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “HPC MW energized in 1H of 2025”
confirms core-scientific 8-K exhibit (ef20057996_ex99-1.htm)
Quote: “~120+ MW Energized Across Denton & Marble Sites”