382 MW HPC infrastructure delivery
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
Company-wide billable capacity was 395 MW at June 30, 2026 and 485 MW at September 30, 2026, but no passage links these figures to the 382 MW infrastructure program or its five data centers. The numbers may use different measures of capacity, and they do not show whether this specific scope was completed on schedule.
“The gap between Leased Customer Power Capacity and Billable Customer Power Capacity represents contracted capacity for which we are constructing and commissioning infrastructure”
2026-07-27 · Core Scientific 10-Q filed 2026-07-28 View cached copy (2026-08-30)Live source ↗
“Leased Customer Power Capacity 1,120 590 590 Unleased Customer Power Capacity 555 685 330 Billable Customer Power Capacity 485 395 120”
2026-11-04 · Core Scientific 10-Q filed 2026-11-05 View cached copy (2026-11-06)Live source ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core Scientific estimates delivery of its 382 MW of HPC application-specific data center infrastructure across five data centers in phases from H2 2024 through H1 2026.
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 H1 2025 H2 2025 H1 2026”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 H1 2025 H2 2025 H1 2026”