Uncontracted critical IT load

Company: Core Scientific

Subject kind
facility capacity
Statement date
2025-02-26
Promised amount
70.0 MW
Current status
stated

The claim, verbatim

About 70 MW of critical IT load is available to contract.

Source (primary)

Fourth Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “~70 MW critical IT load available to contract1”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Fourth Quarter Fiscal Year 2024 Earnings Presentation

Quote: “~70 MW critical IT load available to contract1”

View cached copy (2026-11-06)Live source ↗Archive.org ↗