~155 MW cumulative delivery by Q3 2025

Company: Core Scientific

Subject kind
facility timeline
Statement date
2025-05-07
Promised by
2025-09-30
Promised amount
155.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

Late-October 2025 materials, published after the Q3 target date, report about 120+ MW energized at Denton and Marble, below the roughly 155 MW scheduled. The figure excludes Austin and uses 'energized' rather than 'delivered', so the exact shortfall is unclear.

“~120+ MW Energized Across Denton & Marble Sites”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗

Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The delivery schedule shows about 90 MW added in Q3 2025, for about 155 MW delivered cumulatively.

Source (primary)

First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “~155 MW delivered + ~90 MW”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms First Quarter Fiscal Year 2025 Earnings Presentation

Quote: “~155 MW delivered + ~90 MW”

View cached copy (2026-11-06)Live source ↗Archive.org ↗

Record of changes

November 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 6, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.