~155 MW cumulative delivery by Q3 2025
Company: Core Scientific
What the later record shows
Partly delivered
Late-October 2025 materials, published after the Q3 target date, report about 120+ MW energized at Denton and Marble, below the roughly 155 MW scheduled. The figure excludes Austin and uses 'energized' rather than 'delivered', so the exact shortfall is unclear.
“~120+ MW Energized Across Denton & Marble Sites”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The delivery schedule shows about 90 MW added in Q3 2025, for about 155 MW delivered cumulatively.
Source (primary)
First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “~155 MW delivered + ~90 MW”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms First Quarter Fiscal Year 2025 Earnings Presentation
Quote: “~155 MW delivered + ~90 MW”